ITNL has been involved in the development and implementation of important Highways,
Flyovers, Bridges and Roads. These projects have been designed on international
standards in terms of technology and facilities. These Roads are strategically important
as they connect major industrial and social centres of the country.
Barwa-Adda-Panagarh Section of NH-2
The objective of the Project is to retrofit a six-lane cross-section on to existing 4-lane highway such that the safety and efficiency of the traffic flow on the project road is enhanced with minimal adverse impact on local populatio
|
View Larger Map
|
Project
|
: |
Barwa Adda Expressway Limited
|
Authority
|
: |
National Highways Authority of India |
Concession Period
|
: |
20 yrs |
Supervision Consultant
|
: |
- |
EPC Contractor
|
: |
ITNL |
O&M Contractor
|
: |
ITNL |
Project Length (Km / Lane km) |
: |
122.88 km |
Date of Signing of Concession Agreement
|
: |
08-05-2013 |
Date of Financial Closure
|
: |
In progress |
Concession Period
|
: |
20 yrs |
Appointed Date
|
: |
04-11-2013 (Scheduled) |
Schedule Project Completion Date (SPCD)
|
: |
910 days from Scheduled Appointed Date |
Concession Ending in |
: |
2033 |
Flexible Pavement
|
: |
122.88 kms |
Service Road
|
: |
149.310km |
Major Bridge
|
: |
3 |
Minor Bridge
|
: |
20 |
Grade Separator
|
: |
12 |
Box / Pipe / Slab Culvert
|
: |
203 |
Under Pass
|
: |
35 |
ROB |
: |
2 |
At Grade Junction |
: |
- |
Bypass Length |
: |
8.12km |
Toll Plaza |
: |
2 |